Policy Guidelines for Managing Variation Orders in Philippine Water and Wastewater Projects Using Analytical Hierarchy Process
DOI:
https://doi.org/10.31098/lomr.v4i2.3654Keywords:
Variation Order, Project Cost, Water and Wastewater ProjectsAbstract
This study aimed to identify and analyse the impacts of variation orders on project costs in selected water and wastewater projects in the Philippines using the Analytical Hierarchy Process (AHP). Specifically, the study sought to determine and rank the most critical causes of variation orders and to propose a policy guideline to minimize their impacts on project costs. A mixed-methods approach was employed, involving surveys administered to experts directly involved in water and wastewater projects. Responses were evaluated using the AHP technique, which enabled the prioritization of the identified causes based on their relative influence. The results revealed that design changes, errors and omissions in design, and changes in project scope were the top contributing factors to variation. These causes were found to significantly affect project cost, leading to increased expenditures and potential delays. Consequently, the desire for profit and the ambiguous design from the consultant are driving variation, impacting cost as well. Through the AHP, a pairwise comparison matrix was developed, which established a consistent and structured ranking of these causes based on expert judgment. The study concluded that effective planning to finalize the scope, enhanced stakeholder coordination, and improved design review processes are essential to mitigate the adverse impacts of variation orders on the project cost. A policy guideline was developed to assist agencies in managing and reducing variation-related issues in future projects
References
Albasyouni, W., & Ashraf, M. (2024). Investigating the Causes of Variation Orders in Egypt: Perspective of Medium and Small-Sized Companies. Revista Ingeniería De Construcción RIC, 105–111. https://doi.org/10.7764/RIC.00102.21
Al-Btoush, M. A. (2021). INVESTIGATION ON THE CAUSES AND EFFECTS OF VARIATION ORDERS IN THE CONSTRUCTION PROJECTS IN JORDAN. Journal of Advanced Sciences and Engineering Technologies, 4(1), 65–73. https://doi.org/10.32441/jaset.04.01.07
Alhadithi, W., Naji, H. I., & Zehawi, R. N. (2021b). Identifying the key causes and impacts of variation orders in Iraqi construction projects. Diyala Journal of Engineering Sciences, 14(2), 18–27. https://doi.org/10.24237/djes.2021.14202
Alhilli, H. K., & Rezoqi, S. I. (2021). Investigating variation orders causes in Iraqi building construction projects. E3S Web of Conferences, 318, 02003. https://doi.org/10.1051/e3sconf/202131802003
Alnuaimi, A. S., Taha, R. A., Mohsin, M. A., & Al-Harthi, A. S. (2010a). Causes, effects, benefits, and remedies of change orders on public construction projects in Oman. Journal of Construction Engineering and Management, 136(5), 615–622. https://doi.org/10.1061/(asce)co.1943-7862.0000154
Alsohiman, N. K., Alattyih, W., & Haider, H. (2023). Ranking of variation orders caused by the owners of construction projects in Saudi Arabia using Statistical and Fuzzy-Based methods. CivilEng, 4(4), 1121–1142. https://doi.org/10.3390/civileng4040061
Alsuliman, J., Bowles, G., & Chen, Z. (2012). Current practice of variation order management in the Saudi construction industry. Procs 28th Annual ARCOM Conference, 1003–1012. https://www.arcom.ac.uk/-docs/proceedings/ar2012-1003-1012_Alsuliman_Bowles_Chen.pdf
Ashworth, A., & Perera, S. (2021). Contractual procedures in the construction industry (8th ed.). Routledge.
Bond University (2021). Sustainable Development Goals. https://bond.edu.au/. https://static.bond.edu.au/sites/default/files/images/SDG%20Poster%20with%20UN%20Emblem_PRINT-2.jpg
Chapman, C., & Ward, S. (2020). Project risk management: Processes, techniques, and insights (3rd ed.). Wiley.
Chen, L., Li, D., & Zhang, S. (2006). A fuzzy synthetic evaluation approach for product quality assessment. Journal of Manufacturing Technology Management, 17(6), 746-761.
Chen, S.-J., & Hwang, C.-L. (1992). Fuzzy multiple attribute decision making: Methods and applications. Springer-Verlag.
Choi, J., Kim, H., & Park, S. (2022). Real-time financial tracking tools and integrated project management software for improved financial reporting and cost control in construction projects. Journal of Construction Engineering and Management, 148(2), 04022002. https://doi.org/10.1061/(ASCE)CO.1943-7862.0002034
CIOB. (2021). Managing change orders in construction projects. Chartered Institute of Building. Retrieved from https://www.ciob.org/research/managing-change-orders
CIOB. (2021). The impact of change orders on construction projects. Chartered Institute of Building. Retrieved from https://www.ciob.org/research/impact-of-change-orders
Cruz, M., Martinez, A., & Lopez, J. (2022). Financial management in construction projects: Addressing the impact of variation orders. Journal of Construction Management, 38(2), 45-59.
Dirgantoro, M. R., & Hardjomuljad, S. (2023). Analysis of the effect of variation order on wastewater projects. Syntax Idea, 5(6), 705–721. https://doi.org/10.46799/syntax-idea.v5i6.2331
Dizon, M., & Reyes, L. (2022). An analysis of the Implementing Rules and Regulations of the Government Procurement Reform Act: Implications for variation order management. Philippine Journal of Public Administration, 59(1), 87-104.
Durdyev, S., & Hosseini, M. R. (2019). Causes of delays on construction projects: a comprehensive list. International Journal of Managing Projects in Business, 13(1), 20–46. https://doi.org/10.1108/ijmpb-09-2018-0178
EDCOP. (2023, June 8). Philippine Water Supply and Sanitation Master Plan - EDCOP. https://edcop.ph/projects/philippine-water-supply-and-sanitation-master-plan/
Enshassi, A., Arain, F., & Al-Raee, S. (2010a). CAUSES OF VARIATION ORDERS IN CONSTRUCTION PROJECTS IN THE GAZA STRIP. Journal of Civil Engineering and Management, 16(4), 540–551. https://doi.org/10.3846/jcem.2010.60
Fernandez, R., & Cruz, J. (2024). Enhancing skills for effective variation order management: Training and capacity-building in the Philippine construction industry. Construction Education Review, 42(3), 112-127.
Garcia, L., & Santos, P. (2023). Standardizing variation order management practices: A case study of construction projects in Metro Manila. International Journal of Construction Research, 15(4), 78-95.
Garcia, M. (2023). The role of clear documentation and stakeholder engagement in effective scope management. International Journal of Project Management, 41(3), 112-121. https://doi.org/10.1016/j.ijproman.2022.11.003
Gardiner, P. D. (2020). Project cost management: Principles and practice. Routledge.
Ghimire, S., Bohra, N., & Awasthi, K. D. (2023). Causes and impacts of variation order in building construction projects: A case study of three projects at Bharatpur Metro. Journal of UTEC Engineering Management, 1(01), 105–114. https://doi.org/10.36344/utecem.2023.v01i01.010
Gould, F. E., & Joyce, N. E. (2020). Construction project management (4th ed.). Pearson.
Hinze, J. (2020). Construction contracts. McGraw-Hill Education.
Ismaeil, E. M. H., & Sobaih, A. E. E. (2024). A proposed model for variation order management in construction projects. Buildings, 14(3), 726. https://doi.org/10.3390/buildings14030726
Jha, K. N. (2020). Construction project management: Theory and practice (3rd ed.). Pearson Education.
Johnson, R., & Patel, S. (2023). Continuous improvement practices and feedback loops in construction quality management. Construction Management and Economics, 41(5), 465-478. https://doi.org/10.1080/01446193.2023.1956407
Kerzner, H. (2022). Project management: A systems approach to planning, scheduling, and controlling. Wiley.
Koirala, N. (2021). Variations Order of Building Construction Project a Case from Nepal. Journal of Advanced Research in Construction & Urban Architecture, 6(2), 25–33. https://doi.org/10.24321/2456.9925.202105
Kuei, C., & Madu, C. N. (2021). Quality management in construction projects. Springer.
Larson, E. W., & Gray, C. F. (2021). Project management: The managerial process (8th ed.). McGraw-Hill Education.
Lee, A., Chen, B., & Wong, T. (2022). Preventing scope creep through robust scope management frameworks. Journal of Project Management, 39(4), 98-108. https://doi.org/10.1007/s40799-021-00556-6
Li, Y., Chen, X., Liu, Y., & Jin, H. (2011). Fuzzy synthetic evaluation in project performance assessment. International Journal of Project Management, 29(6), 789-798.
Liu, Y., Zhao, Z., & Li, X. (2021). Enhancing cost prediction accuracy using machine learning in construction projects. Automation in Construction, 127, 103688. https://doi.org/10.1016/j.autcon.2021.103688
Martinez, A., & Lopez, R. (2024). Best practices in variation order management: A comparative study of Philippine and international approaches. Global Construction Review, 19(1), 56-74.
Mashamba, T., Kanakana-Katumba, M., & Maladzhi, R. (2023). VARIATION ORDERS DURING EXECUTION OF CONSTRUCTION INFRASTRUCTURE PROJECTS: CASE STUDY OF AN ELECTRICITY COMPANY. The South African Journal of Industrial Engineering, 34(4). https://doi.org/10.7166/34-4-2898
Mendoza, S., Reyes, J., & Garcia, H. (2021). Documentation and communication challenges in variation order management: Insights from recent Philippine construction projects. Asian Journal of Construction Engineering, 29(2), 33-50.
Meredith, J. R., & Shafer, S. M. (2020). Project management: A strategic managerial approach (10th ed.). Wiley.
Mohammad, N., & Hamzah, Z. (2019b). A review of causes of variation order in the construction of terrace housing projects in Malaysia. MATEC Web of Conferences, 277, 03013. https://doi.org/10.1051/matecconf/201927703013
Mohammad, N., Hamzah, Z., & Mokhtar, N. A. (2022). CONTROL OF VARIATION ORDERS IN THE CONSTRUCTION OF RESIDENTIAL PROJECTS IN MALAYSIA. PLANNING MALAYSIA, 20. https://doi.org/10.21837/pm.v20i21.1088
Mosey, D. (2020). Collaborative construction procurement and improved value. ICE Publishing.
Mubarak, S. A. (2021). Construction project scheduling and control (4th ed.). Wiley.
Muhsen, H. K., & Rezouki, S. E. (2022). The causes influencing the occurrence of variation orders in the construction of buildings. Journal of Engineering, 28(8), 34–53. https://doi.org/10.31026/j.eng.2022.08.03
Oladapo, A. (2007). A quantitative assessment of the cost and time impact of variation orders on construction projects. Journal of Engineering Design and Technology, 5(1), 35–48. https://doi.org/10.1108/17260530710746597
P.D. No. 1594. (n.d.). https://lawphil.net/statutes/presdecs/pd1978/pd_1594_1978.html
Philippines High-Priority Country Plan. (2022). Philippines High-Priority Country Plan. In GLOBAL WATER STRATEGY. https://www.globalwaters.org/sites/default/files/philippines_hpc_plan_508-external.pdf
PMI. (2020). A guide to the project management body of knowledge (PMBOK® guide) (6th ed.). Project Management Institute.
PMI. (2020). Managing contingency in construction projects. Project Management Institute. Retrieved from https://www.pmi.org/learning/library/managing-contingency-construction-projects-11234
PMI. (2020). Time management in construction projects. Project Management Institute. Retrieved from https://www.pmi.org/learning/library/time-management-construction-projects-11045
PMI. (2020). Understanding the project management triangle. Project Management Institute. Retrieved from https://www.pmi.org/learning/library/project-management-triangle-10161
PMI. (2021). Project success factors: What makes a project successful? Project Management Institute. Retrieved from https://www.pmi.org/learning/library/project-success-factors-11758
PMI. (2021). Scope management in construction. Project Management Institute. Retrieved from https://www.pmi.org/learning/library/scope-management-construction-projects-11807
Republic Act No. 9184. (2003). Government Procurement Reform Act. Retrieved from https://www.officialgazette.gov.ph
RIBA. (2020). Client responsibilities in construction projects. Royal Institute of British Architects. Retrieved from https://www.architecture.com/knowledge-and-resources/knowledge-guide/client-responsibilities
Saki, R., & Yeom, C. (2022). Causes of variation orders in road construction projects in Tanzania. ˜the œOpen Transportation Journal, 16(1). https://doi.org/10.2174/18744478-v16-e2208182
Smith, J., & Wilson, D. (2023). Agile project management and BIM for improved planning accuracy and timeline adherence. Journal of Building Engineering, 59, 104154. https://doi.org/10.1016/j.jobe.2022.104154
Tedja, B. A., & Rarasati, A. D. (2021). Development in design stage based on risk to reduce variation order in building construction project at PT. XYZ. Journal of International Conference Proceedings, 4(3). https://doi.org/10.32535/jicp.v4i3.1350
Villar, D., & Garcia, M. (2023). Developing standardized procedures for variation order management: Lessons from Philippine construction projects. Journal of Construction Administration, 40(2), 21-37.
Walker, A. (2020). Project management in construction (7th ed.). Wiley-Blackwell.
Yana, A. G. A., HA, N. R., & Wibowo, M. A. (2015). Analysis of Factors Affecting Design Changes in Construction Project with Partial Least Square (PLS). Procedia Engineering, 125, 40–45. https://doi.org/10.1016/j.proeng.2015.11.007
Yang, H., Sun, Y., & Zhang, L. (2022). Delay mitigation strategies in construction project scheduling. Engineering, Construction and Architectural Management, 29(6), 1967-1982. https://doi.org/10.1108/ECAM-02-2021-0152
Zhao, J., Li, H., & Xu, Y. (2021). Automated quality control systems in construction: The role of drones and sensors. Journal of Quality in Maintenance Engineering, 27(4), 653-668. https://doi.org/10.1108/JQME-04-2020-0035
Zwikael, O., & Smyrk, J. (2020). Project success and management: Defining, measuring, and applying the right metrics. Springer.
Downloads
Published
Citation Check
How to Cite
Issue
Section
License
Copyright (c) 2025 Misael Jr L Camposano, Arvin R De La Cruz, Joseph Raniel A Bianes

This work is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License.
Content Licensing, Copyright, and Permissions
1. License
Logistic and Operation Management Review (LOMR) has CC-BY NC or an equivalent license as the optimal license for the publication, distribution, use, and reuse of scholarly work for non-commercial purposes. The non-commercial use of the article will be governed by the Creative Commons Attribution license as currently displayed on Creative Commons Attribution-NonCommercial 4.0 International License
Creative Commons License
2. Author’s Warranties
The author warrants that the article is original, written by stated author(s), has not been published before, contains no unlawful statements, does not infringe the rights of others, is subject to copyright that is vested exclusively in the author and free of any third party rights, and that any necessary written permissions to quote from other sources have been obtained by the author(s).
3. User Rights
Logistic and Operation Management Review (LOMR) objective is to disseminate articles published are as free as possible. Under the Creative Commons license, this journal permits users to copy, distribute, display, and perform the work for non-commercial purposes only. Users will also need to attribute authors and this journal on distributing works in the journal.
4. Rights of Authors
Authors retain the following rights:
Copyright, and proprietary rights relating to the article, such as patent rights,
The right to use the substance of the article in future own works, including lectures and books, The right to reproduce the article for own purposes, The right to self-archive the article, the right to enter into separate, additional contractual arrangements for the non-exclusive distribution of the article's published version (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this journal (Logistic and Operation Management Review (LOMR).
The author has a non-exclusive publishing contract with a publisher and the work is published with a more restrictive license, the author retains all the rights to publish the work elsewhere, including commercially, because she/he is not subject to the conditions of her / his own license, regardless of the type of CC license chosen.
5. Co-Authorship
If the article was jointly prepared by other authors, the signatory of this form warrants that he/she has been authorized by all co-authors to sign this agreement on their behalf, and agrees to inform his/her co-authors of the terms of this agreement.
6. Termination
This agreement can be terminated by the author or Logistic and Operation Management Review (LOMR) two months’ notice where the other party has materially breached this agreement and failed to remedy such breach within a month of being given the terminating party’s notice requesting such breach to be remedied. No breach or violation of this agreement will cause this agreement or any license granted in it to terminate automatically or affect the definition of Logistic and Operation Management Review (LOMR).
7. Royalties
This agreement entitles the author to no royalties or other fees. To such extent as legally permissible, the author waives his or her right to collect royalties relative to the article in respect of any use of the article by This agreement can be terminated by the author or Logistic and Operation Management Review (LOMR) upon two months’ notice where the other party has materially breached this agreement and failed to remedy such breach within a month of being given the terminating party’s notice requesting such breach to be remedied. No breach or violation of this agreement will cause this agreement or any license granted in it to terminate automatically or affect the definition of the Logistic and Operation Management Review (LOMR) or its sublicensee.
8. Miscellaneous
Logistic and Operation Management Review (LOMR) will publish the article (or have it published) in the journal if the article’s editorial process is successfully completed and the logistics and Operation Management Review (LOMR) or its sublicensee has become obligated to have the article published. Logistic and Operation Management Review (LOMR) may conform the article to a style of punctuation, spelling, capitalization, referencing, and usage that it deems appropriate. The author acknowledges that the article may be published so that it will be publicly accessible and such access will be free of charge for the readers